After more of a wait than was ideal, SSE finally turned up and connected us (after two attempts).
I now have our MPLAN number and Eon will be coming with a metre in a couple of weeks.
...
We've now appointed an internal project manager who is co-ordinating the trades (and very handy himself) and we've made a start on plumbing, done 1st fix of electrics.
and for Passivehuis-ness, we've completely membratnes the internal walls. A massive job that will never be seen once plasterboard goes on.
...
After more hiatus, our structure has its cladding (mainly) - we've now put all outside work on hold until Spring and will start on the inside fixes. So soffit and barge boards, balconies and balustrades will have to wait a while.
...
Although you can see the odd gap, which will be filled by the time I blog next, our rather large 5.8m wide sliding glass doors (and essentially the 4th wall) are now in.
Just four weeks to go and the shell is clad and complete and 1st fix can start - probably in New Year as things will stop for Xmas.
...